Main St Landing Update

Main St Landing Update
Posted on 12/06/2019
Main St Landing Update

Hindered by spring flooding, the Main St Landing flexible event space is on target for completion late spring or early summer 2020, pending weather and spring 2020 river conditions.

Sidewalk installation will be complete in the next week. As planned, finish work is scheduled to begin in early spring.

Items to be finished in next year’s construction season include finalizing plans that incorporate the raised railway into the project, plantings and lighting installation.

Look for more news on this great new addition to the riverfront in 2020.