Eastern Ave Resurfacing

Eastern Ave Resurfacing
Posted on 11/15/2019
Eastern Ave Resurfacing

11/15/19

Eastern Ave will be down to one alternating lane of traffic between E 39th and E 43rd St on Tue Nov 19 for pavement installation.  A flagger will be present.  Consider an alternate route to avoid delays.

Traffic will return to one north and one southbound lane of travel after concrete is poured on Tuesday.

The resurfacing project is estimated to be complete by late November.

11/8/19

Eastern Ave will be down to one alternating lane of traffic between E 39th and E 43rd St on Sat Nov 9 for pavement installation.  A flagger will be present.  Consider an alternate route to avoid delays.

Traffic will return to one north and one southbound lane of travel after concrete is poured on Saturday.

The resurfacing project is estimated to be complete by late November.


10/15/19

Eastern Ave will be closed between E 53rd St and Kimberly Rd on Thursday, October 17th as part of the street re-construction being performed there.  The road is expected to re-open to head-to-head traffic in the east lanes between 43rd and 39th Streets on Friday, October 18th.

When work in the west lanes is complete, travel lanes and construction will flip sides.

Work is estimated to be complete by the end of November.

09/17/19
Beginning Monday, September 23rd, Eastern Ave will be reduced to one lane in each direction between E 39th and E 43rd Streets for street reconstruction and drain tile installation.

Work will begin in the two west lanes; travel will be head-to-head in the east lanes. As work progresses, construction and dedicated travel lanes will flip.

Care should be taken when traveling through the work zone as traffic lanes will be narrowed during construction. Consider taking an alternate route to avoid traffic delays and to increase safety in the work zone.

The reconstruction is estimated to be substantially complete in late November 2019.